Dorsten
Modular building technology for Levi’s European distribution center
Modular building technology for Levi’s European distribution center
© Delta Development
Grid and area plan building parts 1, 2, 3, 4
Modular building technology for Levi’s distribution center
Grid and area plan are
the basis for locating the modules
Grid and area plan are
the basis for positioning the modules
Modularisation building part 1
Aligning the support structure to the grid –
for more equals
Alignment of the support structure to the grid – for more equals
The supporting structure is based on the grid
Control field with high repetition rate of the sprinklers between the PI ribs of the ceiling
Modular planned trades in building parts 1, 2, 3, 4
Technical components with a high repetition rate are planned modularly in building parts 1, 2, 3, 5 and 7
Modular, faster and more flexible construction
Modular, faster and more flexible construction
digitales bauen solutions
Modularization, System integration
(as part of the Drees & Sommer HVAC planning team)
Drees & Sommer solutions
Project management, HVAC planning phases 1-4, LEED certification, sustainability consulting C2C, energy design, façade technology, structural design, building physics
Modular planned trades in the sub-areas 1, 2, 3, 5, 7: Sprinklers, ventilation, smoke extraction, electrical routes, heating and cooling
Project Data
Location
Dorsten
Owner
Delta Development Düsseldorf
General Contractor
Bremer Bau
Client
Drees & Sommer
Architect
Quadrant 4
Owner
70.000 m2
Service Period
2021
Entrance and office of Levi’s distribution center Dorsten
© Delta Development
digitales bauen supported the Drees und Sommer MEP team with its modularization concepts for the Levi Strauss & Co distribution center of Delta Development in Dorsten:
The modularization of the building technology reduces complexity, enables prefabrication, simplifies adaptation to changes and thus increases the quality of the building.
Thanks to its cradle-to-cradle and energy concepts, Levi’s distribution center is considered Germany’s most sustainable logistics center and was nominated in the “Best Industrial & Logistics Project” category at the MIPIM Awards 2024.
Modularly planned areas
The required flexibility of use in the office wing and the high repetition rate of technical components in the logistics halls suggested a modular approach to the technical planning.
Modular planning enables quick changes, modular construction significantly shortens the construction time.
In order to increase the repetition rate of components and enable their prefabrication, the load-bearing structure in logistics hall part 1 was adapted to the building grid.
Flexible use was made possible in the office wing by providing building technology and potential wall positions.
Catalog-based planning
The MEP modules are planned in an integrated manner and arranged by trade in module catalogs. The modules are placed on the floor plans and referenced to a grid.
The MEP modules consist of assemblies, the assemblies of components. By referencing these 3 levels within each other, the amount of data is reduced and changes can be quickly implemented across the board.
Modularization of ventilation and air conditioning building part 1
Catalog-based planning increases construction quality.
Catalog-based planning increases construction quality.
Catalog ventilation and air-conditioning component 1 ground floor
Module plan for ventilation and air conditioning component 1 ground floor
Catalog sprinkler modules in building part 1
Constructive engineering to avoid conflicts on the construction site.
Constructive engineering to avoid conflicts on the construction site.
Catalog sprinkler modules in building part 1
Constructive engineering to avoid conflicts on the construction site.
Changed requirements on a component during planning
Simply change!
Simply change!
Sprinkler component
Sprinkler assembly
With list of referenced components
Sprinkler module
With list of referenced assemblys
Catalogue Sprinkler modules
(Excerpt)
Changed requirements for a component during planning
Simply change!
Simply change!
Sprinkler component
Sprinkler assembly
With list of referenced components
Sprinkler module
With list of referenced assemblys
Catalogue Sprinkler modules
(Excerpt)
80,000 sprinklers in high-bay warehouse building part 3
Referencing instead of copying:
Better 3d model performance
digital planning, constructing
and operating
digitales bauen
Augartenstrasse 1
76137 Karlsruhe
Germany
+49 721 266756 10
info@digitales-bauen.de
© digitales bauen 2025
Legal Notice
Privacy Policy